Victorian progress claims: six months to claim, monthly rights and the Christmas gap
Victoria's Security of Payment changes let subbies claim every month, include variations and delay costs, and stop the clock from 22 December to 10 January. Here is what to do.
Jason, founder of Crewzy ·
Victoria rewrote the rules for progress payment claims on 15 April 2026. The Building and Plumbing Commission says the changes to the Security of Payment Act apply to all construction contracts, including ones signed before that date. Plenty of subbies still work to the old habits, and the Christmas gap is close.
Three changes matter most to a trade business, as the Commission describes them. First, the old limit of three months from the reference date is gone. A claim can now be served up to six months after practical completion (or completion of supply), unless your contract gives a later date. Second, you have a default right to one claim a month, with the earliest date being the last day of the month. A contract term that delays claims past month end, or only allows milestone claims less often than monthly, has no effect.
Third, the "excluded amounts" rules are removed. Claims for latent conditions, time-related costs, regulatory changes and some variations used to be barred, and now they are not.
There are also new limits on the other side. A contract clause that sets payment, or release of security, later than 20 business days after the claim has no effect. A party must give at least 5 business days' notice before going to performance security. And a respondent cannot add new reasons in adjudication that were not in its payment schedule.
Business days now leave out 22 December to 10 January inclusive, according to the Commission. One more December rule: for work done from 22 to 31 December, a contract can set 31 January as the earliest day to serve the claim.
Who it affects
Trade businesses in Victoria that work under a construction contract and claim progress payments: electricians, plumbers, carpenters, concreters and others working for builders or head contractors. The changes apply from 15 April 2026. Other states have their own Acts and different rules, so this does not carry over to them. See security of payment by state.
What to do now
- Look at your current contracts for a claim day. If one says milestone claims only, or a claim date after month end, note that the new default may override it.
- Put a monthly claim on your calendar. Claim each month, not at the end of the job.
- Include variations, delay costs and latent conditions in your claims, not only the base contract work. Keep the paperwork for each one.
- Plan for 22 December to 10 January. Those days do not count as business days. Check whether your contract sets 31 January as the earliest claim day for work done from 22 to 31 December, and diarise it.
- When a payment schedule comes back, read every reason in it. If a reason is missing there, the other side cannot add it later in adjudication.
- For an existing contract, ask a construction lawyer how the rules apply.
How Crewzy helps
Claim every month, on the day
Open the project and use the Claims tab. Set Claim day (day of the month) under Set retention (or Change) on the Retention and invoicing box. If you do not enter one, the claim day is the last day of each month. From a week before, the project shows on Home under Claims due, and if a month passes with no claim, Home notes it, such as "No claim made for August".
See Progress claims and Claim reports, Home and the bell.
Claim the variations on their own line
Each approved variation is claimed on its own line, so the builder sees it apart from the contract work. Pending variations are not on the claim. Approve a variation before the claim, and it goes on.
See Variations.
Keep what went out, and record the schedule
When a claim is submitted, Crewzy keeps its lines and the statement it printed, and files the PDF under Claim files. After the claim goes, you record the builder's payment schedule against it and see when the schedule and payment are due. Crewzy does not know which contract terms now have no effect, and its Security of Payment wording has not been reviewed by a lawyer, so check your contract yourself.
See Payment schedules, invoices and RCTIs.
The honest takeaway
What I can say from the Commission's pages is that the new rules favour the subbie who claims every month and keeps good records. The weak point is the date gap over Christmas.
General information, not legal, tax or safety advice. Check the source and your own adviser.
Sources
Each read on the day shown. Things change, so check the source before you rely on it.
- Building and Plumbing Commission: Changes to the SOP Act, read 27 November 2026
- Building and Plumbing Commission: Changes to the SOP scheme, read 27 November 2026
- Building and Plumbing Commission: Changes affecting construction contracts, read 27 November 2026
- DLA Piper: Victorian security of payment, new regime is in effect, read 26 November 2026